New Facility
Business in Wind’s new facility will be energy efficient, low impact on the environment and a high internal climate standard to ensure the comfort and health of the future user
The way to our new facility
Read the article on Windpowernl to learn more about the story behind our new facility

Excellent performance in the field of sustainability - energy saving, CO2 reduction, good water and waste management - are today's conditions for healthy, conscious and successful business. In the design and realization of the new Business in Wind facility, BREEAM Excellent is the starting point.
BREEAM is the most important and used sustainability label in the world. It involves the use of highly sustainable construction methods and materials. This objectively measurable realization of a very sustainable and partly circular building. This makes the building energy efficient, has a low environmental impact, is low maintenance and represents a higher market value than comparable non-certified projects.
The building will be modeled entirely in BIM. This avoids failure costs and unnecessary material waste to the maximum extent possible.
A procurement strategy has been drawn up, keeping the impact of materials on the environment as low as possible with an LCA (Life Cycle Cost Analysis) for each element.
All wood used in the project is demonstrably certified with an FSC label for sustainable forestry.'With pleasure in your work, safety and quality is no problem'
A sustainability manager will be appointed to set targets and monitor progress during implementation. This will minimize the impact on the environment.
In addition to being energy efficient, maximum effort will be made to ensure the comfort and health of the future user. This includes strict daylight standards, indoor climate requirements and a ban on the use of substances containing volatile organic compounds.
Updates
Business in Wind's new facility will total 4542m2 in size. The start of construction is May 2024. Expected completion is May 2025. Check out the progress of our beautiful construction project on this page. We will regularly post new updates so follow us to keep up-to-date!
August 2025
Now that we have everything set up, we are proud to show you the end result with a series of...
July 2025
From the first working day at the beginning of July on Transportweg, the parking spaces were...
June 2025
The driveway is taking shape, the Smart Energy Storage System is in place, the kitchen has been...
May 2025
The logo is placed, the styling agreed upon, the plumbing is delivered and fitted and the workshop...
April 2025
A wind turbine blade was mounted on the outside of our facility between the office area and the...
March 2025
We make regular rounds with the contractor to discuss finishes. In the office area, all...
February 2025
The frames on the office side were already visible, this month they were filled in with the solar...
January 2025
The nacelle that will soon tower over the new building has been delivered to site, the 2 heavy 2 x...
December 2024
In the exterior facade, the window frames and glass have been installed and inside, the floor...
November 2024
This month, the wall panels were installed, the roof is on and they started to put the glass in....
October 2024
The installer has started, so the spots for the restrooms are already visible. There are colored...
September 2024
Hard work is ongoing. The steel structure is being built. All the steel parts are numbered and...
August 2024
Removal of formwork, refill excavation around basement, preparations for steelconstruction,...
July 2024
Reinforcement steel of ground floor, prepare floor heating for ground floor and concrete...
June 2024
Pooring concrete of the basement and install formwork for for ground floor [gallery...
May 2024
Excavate basement, install anchors and prepare concrete poor by installing reinforcement steel...
Partners
Business in Wind's new facility is being realized with the cooperation of: