You can spot our team this week in Glaubitz, Germany for the decommissioning of Vestas V52s, which were previously owned by WEB.
As gas pipes are crossing this windfarm, precautions and stakeholder management are importent and required.
The team started on Thursday morning at 7 with decommissioning, lifting, the first V52 on 74m tower.
Today, Friday morning at 11, the first two are completely gone. This is not because of a night shift, but reasonable working days and lots of efficiency and motivated teamwork. Preparation is our strength, and as always, this will pay back at the end in safe and efficient projects.
 
Business in Wind will decommission seven V52s 850kW wind turbines on different hub heights the coming period. Several are sold and we have some available. Inspection reports on request, the wind turbines are tidy, well preserved and in good condition.

Want to get updates?

Follow us!