In the last few weeks our teams were involved in several projects, with this post we share an overview.
> Business in Wind supports the installation of an EWT wind turbine on an island of Åland in Finland. Previously we assisted
with the dismantling of this turbine in Sweden.
> Two colleagues from the projects department travelled to Sweden for the preparation to build two E-82s. Among other things, they had an appointment with the crane company and went on site to view the site.
> Locus, Vestas V90-2MW in Värslan, Sweden, delivered power for the first time this week, commissioning is in the final stages.
In Dorset, UK, Alaska wind farm, the four V80s are in their final phase of commissioning.
> In Germany, three Vestas V112 wind turbines were inspected on behalf of Business in Wind.
> Meanwhile in the Netherlands:
* Preparations are underway to ship parts to the US. This is to overhaul three Vestas V80s in Denver, Colorado. These three wind turbines will then be transported to Iowa and California to be rebuilt.
* We disassembled parts for Business in Wind Parts from V66s for sale.
* And we are preparing to change a main bearing from an Enercon E-82 ex Lorup for Locus Färsnas.
These are just some activities outside the door, because of course the staff in the office are also active with all sorts of things. In the meantime the construction of our new building is going very well, but more on that in a later post.
With this post, we share some photos of the activities and at the last two photos you see how our new facility is looking right now.